Panel Replacement Adds Years to Life of Navy Vessel
Panel Built, Inc. (PBI), a portable building manufacturer in Blairsville, Georgia, recently replaced all the wall and roof panels on a two-story US Navy barge deck house that the company had originally installed 30 years ago, giving the vessel new life. The structure, which is used for storage and office space while the barge is docked in Charleston, South Carolina, was in pretty sad shape, patches and repairs giving it a rough look, but it was standing. Now, the commanding officer of the unit that uses the barge said the difference between the condition and appearance from when the barge left their facility to when the project was complete was beyond his expectations of what was possible.
The U.S. Navy worked with Panel Built, Inc. to rebuild a sea-worn two-story deck house barge.
An Unusual Project from the Beginning
Mark Ledger, project manager for BAE Systems Jacksonville Ship Repair, a defense contractor that works on both commercial and military ships, said the project started when they won the contract to perform about 25 maintenance items on a Navy barge, and one of the tasks was to replace the existing deck house structure. “We weren’t familiar with the products or the process because we hadn’t done something specifically like that before,” said Ledger. “We were having difficulty finding sources for the material, so we asked the government, ‘do you have any reference for other companies that have worked on this sort of thing before?’ They recommended Panel Built because, based on the existing design documents, they were the company that constructed the original deck house.”
Eliyah Ryals, outside sales representative for Panel Built, said they didn’t understand the extent of the project until they saw the barge for themselves. “Once we got down to the site,” Ryals said, “we noticed the deck house structure had been through the ringer, you could say. It had been painted over multiple times and was deteriorating due to exposure to the sea. Some panels were in better shape than others, but the whole thing was in pretty bad shape. So, we proposed replacing every panel, the roof, the entire project, basically.”
The original deck house structure had been built and designed by PBI co-founder Michael Tiernan, so the team was able to find the original design documents and work from them. However, with code changes and higher engineering requirements, additional structural elements, including 4,500 pounds of new I-beams and tubular steel, were needed to meet the extreme wind load requirements in Charleston.
A Multitude of Challenges
Ledger said, “the primary design concern and focus was the wind loads. PBI performed a design study to ensure that the modifications made to the structural supports for the walls and roof would withstand those wind loads.” The materials had to be designed to stand up to sea water, salt air, extreme heat, sunlight, humidity, and the occasional hurricane.
Another concern was the weight of the additional elements. “We needed to know the approximate weight of the materials coming off the barge,” said Ledger. “With new materials and construction techniques, some of the additional elements were lighter and some were heavier. We had to calculate the overall weight increase to make sure it wasn’t going to be significant enough to affect the stability of the vessel.”
Because all the walls and roof panels were going to be removed and replaced, BAE constructed an enclosure to keep the space as dry as possible during the construction process. A plastic skin was wrapped around scaffolding to protect all sides of the structure. This made setting panels and getting materials to the barge very difficult, as the plastic had to be moved or removed temporarily while the panels or materials were being set, then closed up again once they are in place. “Because the structural steel was so large and heavy, we had to crane those pieces in through the roof of the containment and then replace it,” said Ledger. “For the roof and wall panels that Panel Built provided, we were able to use articulated forklifts to raise and lower the materials in and out.” Luckily the work was performed in Jacksonville, Florida, so the weather wasn’t much of a factor.
PBI also had to ensure that the structure was sealed properly to prevent leaks and moisture intrusion. “We have buildings all over the US and the world that get rained on and that’s pretty normal for buildings. But with this structure actually sitting on the water on the coast of Charleston, we definitely had to seal it up a lot tighter than usual.”
The refurbished barge was delivered to the Navy in June 2024, ready to serve again.
The Navy requested the same panel finishes as the initial installation, but they were no longer available. “The original building panels had a honeycomb core, which nobody builds anymore, so we had to switch it to a polystyrene core with an aluminum finish, for protection from sea water and rust,” said Ryals.
This project was definitely unusual for Panel Built. Ryals said, “I don’t think anybody really does a bunch of modular buildings on a barge on a normal basis.”
PBI shipped over 120 4’x10’ and 4’x12’ panels in just over four weeks from contract to delivery. The process ran smoothly, and installation was completed without any major issues. The panels come with a ten-year warranty, but Ryals said he wouldn’t be surprised if they lasted another 30 years.
Lessons Learned
Ledger calls the project a “great learning experience” and believes that it will help them in future work. “Some of the lessons learned involve how to disassemble and reassemble these types of modular construction components. We didn’t have much experience with these panels in the past. We have trades here in the shipyard that do similar things, but not with these kinds of materials. It was adapting an existing skillset to a new application. Now, instead of welding steel plate or fabricating something out of sheet metal, if we see that having a prefabricated structure like this would be a better alternative, then this gives us the ability to recognize that.”
Ryals said that while their team was a little leery of the project at the beginning, because of the high potential for something to go wrong, he is glad they took a chance on it because the product is performing well. “This was something that no other company wanted to tackle because they knew the risk. But all in all, it worked out.” He encourages those seeking similar work to contact PBI. “We’ve done it multiple times, so we’re well tooled to do it.”
The barge was delivered to the Navy at the end of June 2024. Here’s hoping the deck house lasts for another 30 years.
About the Author: Dawn Killough is a freelance construction writer with over 25 years of experience working with construction companies, subcontractors and general contractors. Her published work can be found at dkilloughwriter.com.
More from Modular Advantage
How Rebel Concept Harnesses AI as a Design Tool to Improve the DFMA Process
“The complexity of projects and the size of project are so large, and the technology is so complicated that AI would do it so much faster than we are,” says Kris Droszcz, CEO at Rebel Concept. “Everybody’s struggling to control the manufacturing processes according to the design. And I think that’s what AI will do.”
One Answer from AI Can Provide Innumerable Opportunities, says Stack Modular’s Jim Dunn
The Stack AI Engine is not fully functional yet, but it offers an unlimited number of productivity benefits. Currently, the company is using AI for cost estimates, most recently for a project out in California.
GrayWolf: Building the Future of Modular Data Centers to Power the AI Revolution
The growth of artificial intelligence (AI) and cloud-based applications has created an urgent need for data centers capable of managing massive amounts of data. As businesses across industries increasingly rely on digital infrastructure to power their AI tools, the demand for data centers has skyrocketed.
Artificial Intelligence: Yes, it is a Construction Game-Changer
Much like other sectors of the economy, AI is reshaping construction, revolutionizing how projects are planned and executed across the country. While it is obvious that AI cannot do certain things by itself, like laying bricks, paving roads, or shingling roofs, its impact stands to be both massive and positive.
The Potential and Possibilities of AI for Offsite
AI is everywhere. Many industries have incorporated AI into business as usual with new organizational structures and new dependencies to be more efficient and to automate repetitive tasks. Offsite construction will not be immune to AI’s ubiquity. The technology offers unique benefits to the offsite building process.
Moving from AI Hype to an AI Advantage
Learning about AI will help you see past the overinflated hype and identify the opportunities specific to your own business. Learning about AI is like peeling an onion – each layer reveals something new, and occasionally it might make your eyes water. But in the end, you’ll have all the ingredients you need to cook up some real innovation in your organization.
The Blueprint for Smart and Ethical AI Integration in Your Business
The journey toward smart and ethical AI integration involves crafting a strategic vision that aligns AI’s transformative potential with your organizational goals. True success with AI is measured by its capacity to enhance human capabilities, foster sustainable growth, and generate value for all stakeholders while actively avoiding ethical pitfalls and harmful risks.
Five Factors for Success When Shifting Your Business to Modular
As labor, competitive and cost factors push more contractors and developers to embrace the opportunity to go modular as a first choice and not a last resort, it’s become clear that adopting this new model requires more than just a willingness to make it happen. Here are five factors to consider as your company moves to a modular construction model:
UniCool-Edge: Optimized Cooling Solutions for Modular and Edge Data Centers
In an industry where efficiency, scalability, and security are crucial, the UniCool-Edge™ system is a revolutionary solution for modular data center manufacturers. By offering external mounting for maximum space utilization, energy-efficient cooling, and pre-commissioned reliability, UniCool-Edge helps manufacturers stay ahead in the rapidly evolving AI-driven data center market. As edge data centers continue to expand, solutions like UniCool-Edge will play a vital role in supporting the next generation of modular data centers and their data center infrastructure.
Building Skills in a Virtual World: Immersive Training for the Modern Workforce
As both the hardware and software for developing and deploying XR applications continue to become more affordable, the investment in this technology as a training tool is increasingly appealing. XR also offers several other benefits, including performing potentially hazardous tasks in a safe environment and acquiring new skills without the immediate need for physical materials.