BISD Legacy Fund Athletic Projects

(Click an image below to see enlargement)
Main Category:
Modular Building Design
Company:
Aries Building Systems, LLC
Affiliate:
Aries Building Systems, LLC
Location:
Haltom City, TX
Building Use:
Locker Rooms & Concession
Gross Size of Project:
7104 Square Feet
Days to complete:
91

Award Criteria

  1. Architectural Excellence
    Challenged with a tight budget and even tighter timeline, Aries Building Systems, LLC relocated and set up a fully operational athletics facility on time and under budget. The structures that were designed, fabricated and installed by Aries include a new state-of-the-art soccer/football turf field, a new state-of-the-art 6 lane track and all new field events apparatus. The project also required construction of new modular concession stand and restroom facility for the new soccer/track/football complex and new on-site dressing room for the softball and baseball fields. The design team were able to integrate several custom specifications and utilize a sizeable pre-built inventory to take advantage of current market conditions and minimize construction delays. The Modular construction project was completed using a combination of steel supporting structures with wooden modules, this amalgamation of materials ensures that the entire complex is longer lasting than standard builds.
  2. Technical Innovation & Sustainability
    The budget and deadline requirements set forth by Birdville ISD meant that Aries Building Systems had to build and deliver an appealing selection of TEA compliant sporting facilities in record time. By utilizing its “Turnkey Advantage,” Aries showcased their competence by building, transporting, and working on-site to install the modular science labs for the school district, enabling students to benefit from the enriched programs being provided in these units. The offsite construction technique for this project captured many of the typical modular construction advantages but were modified to be successful in an high traffic environment.
  3. Cost Effectiveness
    Modular Buildings were delivered to site on solid tensioned slab foundations engineered to withstand industrial PSI ratings. This technology eliminated many of the costs and typical delays caused by weather, inspections to permitting focus to be invested in other on-site construction problems that often occur. This also provided an easy way to add value by expanding all modular buildings without interrupting business. The modular buildings can be easily relocated at a fraction of the cost of new construction.